General Characteristics
T2 V84.3 A gas turbines
2 heat recovery boilers
1 steam turbine
Power
Simple cycle 2 x approx. 157 MW Combined cycle 160 MW TV + 25 MW
Additional fire, approx.
Installed capacity: 485 MW Effective capacity: 479.3 MW
Commissioning
First boiler: July 2006 Second boiler: September 2006
Location: District of Ventanilla, Province of El Callao. Type: Combined cycle thermal power plant.