N° | Section of Resolution |
Responsible |
Information |
Via |
Term |
1 |
6.1.1 |
Customer |
Information for RACG study |
Letter to COES |
31 March |
2 | 6.1.2 |
COES |
Non-compliance of the information delivery for the RACG study |
GFE Portal |
15 April |
3 | 6.2.2 |
COES |
Preliminary report on RACG study |
GFE Portal |
31 August |
4 | 6.2.3 |
Customer |
Observations to the Preliminary Report of RACG study and delivery of load deagrams to COES |
Letter to COES |
15 September |
5 | 6.2.4 |
COES |
Final report on RACG study. Technical Specifications of RACG Protection Schemes (F02, F03 and F04) |
GFE Portal |
30 September |
6 | 6.3.1 |
Customer |
Offers for ERACMF or exchange of ERACMF |
GFE Portal |
15 October |
7 | 6.3.2 |
COES |
Contribution to ERACMF |
GFE Portal |
15 November |
8 | 6.3.3 |
Customer |
Implementation of ERACG (F06C, F07A, F08) |
GFE Portal |
2 January |
9 | 6.4.1 |
COES |
Registration of RACG events |
GFE Portal |
4 hours after the event |
10 | 6.4.1 |
Customer |
Register of ERACG performance |
GFE Portal |
60 hours after the event |
11 | 6.4.1 |
COES |
Technical Report on Performance Evaluation |
GFE Portal |
30 working days after the event |