Energy Demand in San Martín de Porres, San Miguel and Callao to Be Met

Published on Wednesday, 23 September 2015

Enel Distribución Perú increased the output of one of its transformers in the Barsi Transmission Substation.

Lima, 23 September 2015 – In order to meet the energy demand of customers in the districts of El Callao, San Miguel and San Martín de Porres, Enel Distribución Perú has increased from 85 MVA to 180 MVA the output of one of its transformers in the Barsi Transmission Substation.

This project is part of the company’s transmission plan approved by the Peruvian Supervisory Agency for Investment in Energy and Mining and helps provide energy support for the development of production activities in the city.

It should be noted that the increase was carried out within the expected timeframes and with zero accidents. The transformer came into operation at 00:30 a.m. on 14 September.

Enel S.p.A. provides for the dissemination to the public of regulated information by using SDIR NIS, managed by BIt Market Services, a London Stock Exchange Group's company, with registered office at Milan, Piazza degli Affari, 6. For the storage of regulated information made available to the public, Enel S.p.A. has adhered, as from July 1st, 2015 to the authorized mechanism denominated “NIS-Storage”, available at the address www.emarketstorage.com, managed by the above mentioned BIt Market Services S.p.A. and authorized by CONSOB with the resolution No. 19067 of November 19th, 2014. From May 19th 2014 to June 30th 2015 Enel S.p.A. used the authorized mechanism for the storage of regulated information denominated “1Info”, available at the address www.1info.it, managed by Computershare S.p.A. with registered office in Milan and authorized by CONSOB with resolution No. 18852 of April 9th, 2014